Photograph by George Sakkestad
Kimo Watry installs new plumbing in one of Los Gatos High School's restrooms as part of the renovation project.
|
Renovation projects under way at Los Gatos, Saratoga high schools
By Jason Baker
Saratoga and Los Gatos high school construction projects could be completed sooner than anticipated--with money to spare--if a newly adopted implementation plan goes according to schedule.
Los Gatos-Saratoga Joint Union High School District trustees on Aug. 3 approved the hiring of Gilbane Building Company to oversee project management and construction management services for the district's $79 million renovation and construction project.
The board additionally approved a refined implementation plan presented by Gilbane that shortens the time for project completion from 10 years to about six years. Barring unforeseen complications, officials said, the newly adopted plan should also allow for an estimated $2.8 million in contingency money that could be used by the district for additional projects.
Voters in June of 1998 passed the Measure B bond initiative to fund renovation and construction. To fund the measure, homeowners will pay an average of $35 per $100,000 of assessed property value, not market value. Geoff Teall, assistant superintendent of administrative services/chief business officer, said that rate should not change under the new plan. As with the original plan, the rate is subject to the rate of property value growth in the district, which continues to increase yearly.
"We think if the rate of growth continues, even at a lower rate, the $35 average will not change," Teall said. "It could very well be less."
Essentially, by compressing the length of time needed for project completion, the revised implementation plan saves money that would be lost to inflation during the additional four years, Teall said. The first $20 million of bond money was issued earlier this year, with three more series of bonds to be issued in the future.
"I think the Gilbane company has done a marvelous service and provided a brilliant plan for us," he said.
Bob Crowder, Gilbane's project executive, said the revised implementation plan condenses the project schedule but allows more time for each project by scheduling work year-round instead of just six months a year as in the original plan. But the plan won't mean a lot of work being done at one time, which could disrupt students and teachers, he said.
It instead employs engineering and coordinating project flow, allowing work to be done on buildings that are not occupied and float time between projects as needed. The revised implementation plan targets all projects for completion by 2004.
The selection of Gilbane came after the district submitted a public request for proposals to find a construction-management firm for the project. Richard Meyer, district director of building projects, said that in regard to the specific qualifications the district sought in a construction-management firm, the Gilbane proposal received the highest marks. The company's history and experience, integrity, toughmindedness and teamwork made Gilbane stand out above other bidders, he said.
The trade publication Engineering News Record recently ranked Gilbane second in the country among construction managers of education facilities. The firm has managed or constructed school facilities totaling more than $1 billion since 1990. Educational facilities represent about 42 percent of the company's annual new contracts.
This summer, workers began the first projects, which included mechanical renovation and restroom upgrades at both campuses. Meyer also said workers repaired an additional 30,000 square feet of roofing at Saratoga High, which had been a source of ongoing problems. The summer projects are scheduled for completion on Aug. 27.
|
 |
|
 |
 |
|
|
 |
|
Los Gatos Rowing Club hosts successful summer camp for youth
|
 |
|
News Briefs
Town considers closing on-ramp during Highway 17 traffic jams
Wildlife Center stops accepting animals from Los Gatos
Los Gatos Mobile Home Park dispute sent to mediation
Council sends apartment proposal back to Planning Commission
|
 |
|
Letters
Editorial: Traffic congestion could be profitable
Space exploration is a worthy pursuit
|
 |
|
High School renovation may finish ahead of schedule
|
 |
|
The Prowler
Los Gatos Museum hosts exhibits by George Rivera, Randall Shiroma
Births
Weddings
Obituaries
|
 |
|
News from area businesses
|
 |
|
Main Street
Picture From the Past
|
 |
|
Mulching keeps moisture in soil, sun and weeds out
|
 |
|
Saveur Specialty Foods offers tapenades, recipes
|
 |
|
Sports Briefs
Dammit Run returns for 26th year
Courtside Tennis Center sends teams to junior championships
Photo: Little League 'Black' all-stars
Photo: Little League 'Orange' all-stars
Photo: Local soccer star Marcia Wallis
|
 |
|
Lectures, readings, auditions, sports & recreation,announcements, theater & arts, kids' stuff, clubs, public meetings...
|
 |
|
Something to say?
|
 |
|