The Sun periodically provides updates on the $400 million Town Center redevelopment project headed by Sand Hill Property Co.
*Construction of parking garages in the two westerly blocks of the development continues on the third level of each garage.
*The easterly project fence in the Macy's parking lot will be moved in the next few weeks to permit work on building pads south of Macy's.